Bridgnorth bypass roadworks

Significant improvement works are to be carried out between July and November on the A458 Bridgnorth bypass and the roundabout approaches between the Wenlock Road junction and the Stourbridge Road roundabout. The bypass project will see the replacement of bridge expansion joints on the Bridgnorth River Severn Bridge, along with concrete repairs to the bridge and works on the bridge parapets.

The Severn Valley Railway Overbridge will be repainted, roundabout approaches will be resurfaced, signs and markings will be replaced and refreshed and footpaths repaired; street lighting and safety barriers will also be updated and drainage improvements carried out.
Work is due to start on 11 July and finish by 10 November, with traffic signals and lane closures from 11 July to 7 August, and a series of overnight closures throughout August and October.

Share:

Facebook
Twitter
Pinterest
LinkedIn
On Key

Related Posts

Ludlow Food Festival playing with fire

 Ludlow Food Festival celebrates its 30th anniversary this September.  This vibrant three-day celebration highlights the Marches region’s rich heritage of great food and drink, from

Shifnal race boosts good causes

Five good causes have received a boost thanks to Shifnal’s 10K race. The sell-out event in April was organised by a group of the town’s

A woodland tail

On a family holiday, Ed has his first ever sighting of a rare British treasure. The bird hide overlooks a woodland glade. At first glance

Summer sowing

Ann looks forward to the new season. There’s plenty to keep you busy in the vegetable plot at the moment. Plant smaller quantities little and

Learning in the great outdoors

Neil Thomas looks at the work of a charity promoting a deeper love of the natural world. It is the UK’s leading environmental education charity